Building windows

COVID-19 Coronavirus as a Force Majeure Defense to Contractual Non-performance

One often doesn’t know the extent of one’s insurance coverage until a calamity occurs. So it is with force majeure provisions in contracts

Typically, force majeure provisions are included in contracts to excuse a party from contractual obligations if some unforeseen event beyond its control prevents performance of its contractual obligations.

As of March 2, 2020, there have been 88,948 confirmed cases of this strain of the coronavirus (COVID-19) in 64 countries with 3,043 confirmed deaths. The first reported case of COVID-19 was just over two months ago on December 31, 2019 from Wuhan, China. The effects of this coronavirus have already prevented or delayed performance in countless agreements in numerous industries causing widespread commercial loss and business interruption. It is likely that travel restrictions, worker shortages, immigration quarantines, supply-chain disruptions, and event cancellations will worsen before they begin to recover. And now, those affected are dusting off their agreements to examine their force majeure provisions and determine whether they might cover a coronavirus event.

Background

The concept of force majeure (meaning superior force) originated in the Napoleonic Code of 1804. The breaching party to an agreement was condemned unless their non-performance or delay in performance resulted from a cause that could not be imputed to them, and by a cause of a superior force or of a fortuitous occurrence. Today, most tribunals, both in common law and civil law systems, recognize that contractual performance that becomes impossible or commercially impracticable under certain contexts may be excused. That said, the words in the parties’ force majeure provision controls, and that provision is deemed to be the parties’ negotiated allocation of who bears the risks of particular catastrophic events as between them.

Force majeure provides an excuse for a party’s non-performance of its contractual obligations as a result of an extraordinary event or circumstance beyond the control of the parties, such as act of God, war, strike, riot, etc.

What law governs the contract? Common law or civil law principles?

Unless there is an express provision in the contract, force majeure does not exist as a standalone defense in common law jurisdictions such as the U.S. and the U.K. In civil law jurisdictions, such as France and Germany, however, force majeure is implied into every contract, unless the parties agree otherwise. In order to minimize unintended consequences, contracting parties in both jurisdictions include force majeure provisions in their agreements.

In common law jurisdictions, the general rule is strict liability for the breach of a contract. This reflects the principle of pacta sunt servanda (preserving the sanctity of the contract). But there are exceptions. Common law jurisdictions excuse performance when it is not practical and could only be done at excessive and unreasonable cost. In the U.S., the Restatement (Second) of Contracts § 261 (1981), states:

“Where, after a contract is made, a party’s performance is made impracticable without his fault by the occurrence of an event the non-occurrence of which was a basic assumption on which the contract was made, his duty to render that performance is discharged, unless the language or the circumstances indicate the contrary.”

In the U.K., the similar doctrine of “frustration of purpose” is likewise a defense to non-performance. Frustration of purpose occurs when an unforeseen event undermines a party’s principal purpose for entering into a contract such that the performance of the contract is radically different from performance of the contract that was originally contemplated by both parties. Whether under an “impracticable” or “frustration” jurisdiction, the standard for relief is a high one, and is subjective. That subjectivity can only be definitively resolved by litigation and judicial intervention.

Specify conditions short of “impracticable”

To avoid the uncertainty of such subjective standards, contracting parties in common law jurisdictions typically include force majeure provisions to specify events or circumstances that will excuse performance of contractual obligations by a party. Such specified force majeure events might not rise to the level of “impracticable” or “frustration.” By negotiating force majeure provisions, the parties can better allocate the consequences of non-performance as between themselves. For example, in a supply contract for the purchase of medical grade masks, if the manufacturer/seller is suddenly unable to timely deliver the masks to the buyer because of a trucking strike, the manufacturer could suffer the consequences of the substantially increased costs of delivering the masks by a private carrier. So long as the delivery costs are not prohibitively higher, the manufacturer will be liable for breach of contract if the manufacturer does not perform.

The doctrines of “impracticable” or “frustration” are of no avail in these circumstances. And even if they might be available, the application of them would have to be litigated. But if a properly worded force majeure provision is in the contract it could excuse performance in the event of trucking strikes, and the manufacturer would be off the hook.

In civil law jurisdictions, the doctrine of force majeure is implied, irrespective of whether the contract expressly contains a force majeure clause. The problem is that each civil law jurisdiction has some differences as to when the implied force majeure is an available excuse for non-performance, and also as to what consequences or remedies are available when implied force majeure applies. So, even in civil law jurisdictions, the parties commonly include their own tailor-made force majeure clauses to identify particular events that will unequivocally qualify as excuses for non-performance and of the consequences for non-performance.

Importance of foreseeability of the event

In both common law and civil law jurisdictions, foreseeability is a primary factor in the determination of whether a non-performance will be excused. If an event is foreseeable, the happening of the event is an excuse for non-performance if the event is specifically included in a force majeure clause. When a foreseeable event occurs that is not specifically included in a force majeure clause, the non-performing party suffers the consequences. When an unforeseeable event occurs, and the burden of performance rises to the level of impracticable without fault, the non-performance may be excused – even without a force majeure clause. When an unforeseeable event occurs, and the burden of performance is below the level of impracticable, the non-performance will not be excused.

The fact is, many events are foreseeable and therefore the parties should allocate the risk and the consequences of a foreseeable event happening in a force majeure clause, based on the economics of the transaction and the party most willing and able to bear the risk. Tribunals in both common law jurisdictions and civil law jurisdictions reason that if the parties provided a force majeure clause in their contract, then the failure to include a foreseeable calamitous event is an assumption of the risk of that event by the non-performing party. The decisions where tribunals reject a force majeure defense are based on the conclusion that the party proffering the defense could have and should have identified the event that led to the non-performance and should have specifically allocated for that risk before entering into the contract.

What to put in the force majeure clause

Accordingly, the force majeure clause should include every foreseeable event to which the parties agree will provide an excuse for non-performance because, again, tribunals hold that if the event is not listed in the force majeure clause, then non-performance is not excused. And specificity for an event is important. The words matter. For example, in a force majeure clause that includes “disruptions from storms,” does that include electrical blackouts from solar storm flares? Is a drought a “natural catastrophe”?

Suppose a force majeure clause that states, “In the event of an epidemic, pandemic, quarantine restriction, or other public health restriction or advisory, the time for the performance of the obligation shall be extended or excused.” Does the present status of the COVID-19 virus fall within an “epidemic”? Is it a “pandemic”? Is a company imposed self-quarantine a “quarantine restriction”? Is a U.S. State Department cautionary travel advisory an “advisory”? So unless the event is specific and the words are clear, then the parties will likely be left with having a tribunal determine whether a non-performance falls within the force majeure clause and whether performance is excused based on general rules of contract interpretation in that particular jurisdiction.

 

Mark Adams is an experienced trial lawyer who focuses his practice on business litigation including contracts, products liability, corporate and partnership disputes, and hospitality litigation. He has wide-ranging trial experience in a variety of commercial disputes, including complex litigation and class actions. He has tried numerous cases in state courts, federal courts, and in domestic and international arbitrations. Mark’s trial wins have been covered by Forbes, Reuters, Life Science Weekly and other publications. Contact Mark at MarkAdams@jmbm.com or 949.623.7202.

This update is provided to our clients, business associates and friends for informational purposes only. Legal advice should be based on your specific situation and provided by a qualified attorney.